Ghadir Louleh Online, the sole exclusive agent of Ghadir Louleh Pasargad; double-wall corrugated pipe, spiral pipe and corrugated pipe fittings at today's factory price with delivery across Iran.

Official factory website: ghadirlouleh.com

  • Corrugated pipe
  • Spiral pipe
  • Corrugated pipe fittings

  • Today’s price list
  • Project purchase inquiry
  • Official agent of Ghadir Louleh Pasargad
  • Agency documents and technical approvals
  • Factory and supply capacity
  • Our services
  • Technical journal
  • Completed projects
  • Track order
  • FAQ
  • Contact us

  • Sales and bulk orders09123837505
  • Rubika: @Ghadirlouleonline
  • Saturday to Thursday, 8 am to 6 pm (Iran time)
  • 021-91094784
  • Head officeShadabad, Tehran
  • Factory and warehouseGarmsar Industrial Park, Garmsar, Semnan, Iran Get directions

Certificates and standards

All certificates

Trust seals

  • National Digital Media Registration (Samandehi)
  • National Union of Online Businesses

© 2026 Ghadir Louleh Online — Exclusive sales agent of Ghadir Louleh Pasargad. All rights reserved.

Terms and conditionsPrivacy policy
HomeProducts
Prices
Home/Blog/Corrugated pipe installation guide: execution steps from trench excavation to watertightness testing
Corrugated pipe

Corrugated pipe installation guide: execution steps from trench excavation to watertightness testing

November 13, 20265 min readBy Ghadir Louleh Online
Corrugated pipe installation guide: execution steps from trench excavation to watertightness testing

Double-wall corrugated pipe is a flexible pipe; in other words, it does not carry soil and traffic loads on its own, but forms a single structure together with the compacted soil around it. For this reason, the quality of installation affects the life of the network as much as the quality of the pipe itself. In this guide we go through the steps of corrugated pipe installation, from trench excavation to the watertightness test.

Before you start: receiving, handling and storing the pipe

  • Check the size, ring stiffness class (SN4 or SN8) and number of fittings against the drawings and the technical specification.
  • Do not throw the pipes during unloading or drag them along the ground; move them with fabric slings or by hand.
  • Stack the pipes on level ground free of stones and sharp objects, and keep the height of the stacks limited.
  • Keep the EPDM gaskets in their packaging until installation, away from direct sunlight, oil and dust.

Step 1: Trench excavation

The trench must be wide enough for a worker to fill and compact both sides of the pipe properly; a trench that is too narrow means the soil beside the pipe cannot be compacted. Level the trench bottom to the design gradient and remove large stones. At large depths and in collapsible soil, slope the trench walls or shore them (with sheeting) for the safety of workers.

Step 2: Bedding preparation

The pipe must not sit directly on a hard or rocky trench bottom. Spread a bedding layer of fine, uniform granular material (sand or fine gravel) free of sharp stones and clods; this layer is usually about 10 to 15 cm thick, and the project's technical specification sets the exact figure. Dig a small recess under the location of each coupler so that the pipe does not ride on the coupler and is supported by the bedding along its entire length. If the trench bottom is loose or saturated soil, replace it with suitable material or reinforce it with geotextile.

Step 3: Laying the pipe in the trench

Install from downstream to upstream, so that the coupler end of each length faces upstream. Lower the pipe gently into the trench with ropes or slings, and never throw it from the edge of the trench. Before joining, check the gradient and alignment of each length; correcting the gradient after backfilling is very costly.

Step 4: Joining with a coupler and EPDM gasket

Corrugated pipe is sealed with a coupler and an EPDM rubber gasket, and no adhesive or welding is required:

  1. Clean the pipe end, the inside of the coupler and the corrugation valleys thoroughly of soil and sand.
  2. Seat the gasket in the specified corrugation valley (usually the first valley from the pipe end) and make sure it is not twisted.
  3. Apply a lubricant made for rubber joints to the gasket and the inside of the coupler; do not use petroleum-based oil or grease, as they damage the rubber.
  4. Keep the pipe coaxial with the coupler and push it home with a lever or hand jack and a protective board; do not strike the pipe directly with an excavator bucket.
  5. Mark the pipe to check that it is fully inserted into the coupler.

Step 5: Backfilling around the pipe (the most important step)

This step determines how much the pipe deforms under load. Place the backfill around the pipe using selected granular material without large stones, in layers and on both sides of the pipe at the same time so that the pipe does not shift. Compact each layer with a hand-held or light compactor, and in particular fill well under the "haunches" of the pipe (the space between the bedding and the lower half of the pipe); this zone plays the greatest role in supporting the pipe. This backfill usually continues to about 30 cm above the pipe crown.

Step 6: Filling the rest of the trench

Once the protective layer over the pipe is in place, the rest of the trench can be filled with suitable soil. Use heavy compactors and rollers only when the soil cover over the pipe is thick enough, and do not allow heavy machinery to cross the pipe route until the minimum design cover is reached.

Step 7: Watertightness testing and inspection

Before handover, test the network with a water or air test in accordance with the project's technical specification (common methods are based on EN 1610). In municipal projects, CCTV inspection of the pipe interior is also carried out to check deformation, settlement and joints. It is best to test section by section and before the trench is completely filled, so that defects are easier to fix.

Summary of the key points of each step

StepKey point
Trench excavationSufficient width to compact both sides of the pipe, and a level bottom at the design gradient
BeddingFine-grained material without sharp stones; recesses under couplers
Laying the pipeFrom downstream to upstream, coupler end facing upstream
JoiningCleaning, gasket in the correct valley, proper lubricant, coaxial insertion
Backfilling around the pipeIn layers, on both sides at once, filling under the pipe haunches
Filling the trenchHeavy machinery only after sufficient cover
TestingWater or air test and CCTV inspection, section by section
Matching pipes and fittings from one factory
Matching pipes and fittings from one factory

Couplers and EPDM gaskets that fit the pipe exactly; corrugated pipe from 110 to 1200 and all fittings direct from the Ghadir Louleh Pasargad factory.

View fittings

Common mistakes in corrugated pipe installation

  • Placing the pipe directly on a rocky trench bottom without bedding
  • Dumping soil onto the pipe from a height, all at once, with an excavator
  • Backfilling from one side only, which pushes the pipe out of alignment
  • Seating the gasket in the wrong valley or installing a twisted gasket
  • Driving trucks and loaders over the trench before sufficient cover is reached
  • Leaving the trench flooded: polyethylene pipe is light and may float in a water-filled trench and lose its gradient

Sourcing pipes and fittings for the job

Buy matching pipes and fittings from one manufacturer so that the coupler and gasket dimensions fit the pipe exactly. Ghadir Louleh Pasargad double-wall corrugated pipe is produced in sizes from 110 to 1200 mm and in classes SN4 and SN8: corrugated pipe sizes and corrugated pipe fittings. If you are undecided between the two classes, read the article The difference between SN4 and SN8 corrugated pipe, and for project advice use the project inquiry form.

Frequently asked questions

From downstream to upstream, so that the coupler end of each length faces upstream. This way each new length seats into the coupler of the previous length, and the line gradient is easier to control.
No. Double-wall corrugated pipe is sealed with a coupler and an EPDM rubber gasket that sits in the valley of the pipe corrugation; only a lubricant specifically for rubber joints should be used.
Fine, uniform granular material such as sand or fine gravel, free of sharp stones and clods. The typical thickness is about 10 to 15 cm, and the exact figure is determined by the project's technical specifications.
Only after the backfill around the pipe has been compacted layer by layer and the soil cover over the pipe has reached the minimum design cover. Crossing earlier can deform the pipe.
Yes, provided the trench is temporarily dewatered during installation and the pipe is prevented from floating, because polyethylene pipe is light. In these conditions class SN8 is usually recommended as well.